Purpose

This workplace lesson requires you to translate an approved operational plan into a practical schedule for one supply chain component. You will determine resource and capacity requirements, arrange required supplies, identify risks and plan responses to performance variances.

Workplace Outcomes

You must be able to:

  • Interpret an approved operational plan.
  • Convert objectives and activities into a workable schedule.
  • Determine resource and capacity requirements.
  • Arrange required goods or services with suppliers.
  • Identify and assess operational risks.
  • Plan responses to overperformance and underperformance.
  • Obtain approval for the completed schedule.

1. Select the Operational Area

Complete the activity for one of the following:

  • Demand execution
  • Transport and distribution
  • Warehousing and facilities
  • Production
  • Procurement and supply

Confirm the selected area, reporting period, operational objective and responsible supervisor.

2. Gather the Required Information

Obtain and review:

  • The approved operational plan
  • Performance objectives and targets
  • Customer or end-user requirements
  • Forecasts and order information
  • Available budget
  • Resource and capacity information
  • Supplier requirements and lead times
  • Existing contracts or service-level agreements
  • Organisational policies and procedures
  • Previous performance reports
  • Known constraints and operational risks

Verify that the documents are current and authorised.

3. Translate the Operational Plan into Activities

Identify:

  • The work that must be completed
  • The required sequence of activities
  • Activity start and completion dates
  • Dependencies between activities
  • Required resources
  • Expected outputs
  • Performance targets
  • Responsible employees
  • Reporting requirements

Break broad operational objectives into activities that can be scheduled, assigned and measured.

4. Determine Capacity Requirements

Calculate the capacity needed to complete the planned work.

Consider:

  • Customer demand
  • Available employees and working hours
  • Equipment and vehicle availability
  • Storage capacity
  • Production capacity
  • Supplier capacity
  • Inventory availability
  • Budget limitations
  • Maintenance requirements
  • Lead times and delivery periods

Record the required capacity, available capacity and any identified shortfall or surplus.

Capacity Comparison

Required capacity variance = Available capacity − Required capacity

A negative result indicates a capacity shortage.
A positive result indicates available surplus capacity.

Capacity Utilisation

Capacity utilisation (%) = (Capacity used ÷ Capacity available) × 100

5. Prepare the Operational Schedule

Record the following information in the schedule:

Activity Start date Completion date Required capacity Responsible person Dependency Performance target

Ensure that the schedule:

  • Supports the approved operational plan.
  • Reflects the correct sequence of work.
  • Accounts for dependencies and lead times.
  • Remains within the approved budget.
  • Uses available capacity effectively.
  • Assigns clear responsibilities.
  • Includes measurable deadlines and targets.

6. Determine Supplier Requirements

Identify any goods or services that must be obtained from internal or external suppliers.

For each requirement, record:

  • Item or service required
  • Required quantity
  • Required delivery date
  • Quality specification
  • Approved supplier
  • Agreed price
  • Contract or service-level requirement
  • Responsible employee

Follow the organisation’s approved ordering and authorisation procedures when placing or requesting orders.

7. Identify Operational Risks

Identify risks that could prevent the schedule from being completed as planned.

Examples include:

  • Supplier delays
  • Inventory shortages
  • Vehicle or equipment breakdowns
  • Employee shortages
  • Incorrect demand forecasts
  • Budget overruns
  • Production interruptions
  • Warehouse congestion
  • Infrastructure disruption
  • Port or border delays
  • Load-shedding
  • Safety incidents
  • Quality failures

Assess each risk according to its likelihood and potential impact.

Risk Likelihood Impact Risk level Preventive action Contingency action Responsible person

8. Plan Responses to Performance Variances

Determine how the organisation should respond when actual performance differs from the schedule.

Underperformance Responses

Possible responses include:

  • Reallocate employees or equipment.
  • Expedite supplier deliveries.
  • Reschedule lower-priority work.
  • Arrange authorised overtime.
  • Use an approved alternative supplier.
  • Revise delivery routes.
  • Correct inaccurate information.
  • Escalate unresolved constraints.

Overperformance Responses

Possible responses include:

  • Confirm that quality requirements were maintained.
  • Review whether excess resources were used.
  • Reallocate unused capacity.
  • Bring forward authorised work.
  • Reduce unnecessary overtime or expenditure.
  • Record successful practices for future schedules.

Define the variance level that will trigger each response and identify who may approve the action.

9. Consult Relevant Stakeholders

Present the draft schedule to affected stakeholders, including relevant:

  • Supervisors
  • Operational employees
  • Suppliers
  • Customer-service employees
  • Finance personnel
  • Warehouse, transport or production personnel

Record stakeholder comments and revise the schedule where necessary.

10. Finalise and Obtain Approval

Before submitting the schedule:

  • Check all dates and calculations.
  • Confirm resource availability.
  • Verify supplier commitments.
  • Confirm that risks and contingency actions are recorded.
  • Check alignment with performance objectives.
  • Confirm that responsibilities are allocated.
  • Obtain the workplace supervisor’s approval and signature.

Workplace Activity

Develop and prepare an operational schedule for one supply chain component over the assigned workplace period.

Your completed work must demonstrate that you:

  1. Interpreted an approved operational plan.
  2. Translated the plan into scheduled activities.
  3. Determined capacity and resource requirements.
  4. Arranged required supplies or services.
  5. Identified and assessed operational risks.
  6. Developed responses to performance variances.
  7. Consulted relevant stakeholders.
  8. Finalised and obtained approval for the schedule.

Required Workplace Evidence

Submit:

  • The approved operational plan or an authorised extract
  • Capacity and resource calculations
  • The completed operational schedule
  • Supplier orders or approved purchasing requests
  • Risk assessment and response plan
  • Records of stakeholder consultation
  • Records of amendments made
  • Supervisor feedback
  • Final operational schedule signed and dated by the workplace supervisor
  • Completed work-experience logbook entry

Confidential organisational information may be removed or anonymised with the supervisor’s approval.

Supervisor Verification Checklist

The supervisor must confirm that the learner:

  • Used an authentic workplace operational plan.
  • Developed a realistic and achievable schedule.
  • Calculated capacity requirements correctly.
  • Followed the organisation’s supplier-ordering procedures.
  • Identified relevant operational risks.
  • Developed suitable variance responses.
  • Consulted affected stakeholders.
  • Complied with organisational policies.
  • Completed the activity within the workplace period.
  • Produced evidence that reflects the learner’s own work.

Lesson Summary

You translated an operational plan into an approved operational schedule, determined capacity and supplier requirements, identified operational risks and planned responses to performance variances. The completed schedule and supporting evidence must be verified and signed by an experienced workplace supervisor.