Purpose of the lesson
Measure actual procurement and supplier performance against operational targets, identify gaps, and develop a practical performance-improvement plan.
Practical outcome
By the end of this lesson, you must be able to:
- Monitor operational procurement activities.
- Measure the placement of supplier orders.
- Measure supplier on-time delivery.
- Measure supplier delivery-in-full performance.
- Monitor quality-related returns.
- Calculate procurement cost per unit.
- Identify procurement bottlenecks and root causes.
- Develop and monitor a performance-improvement plan.
1. Gather the required information
Obtain:
- Procurement operational plan
- Approved performance targets
- Purchase requisitions
- Purchase-order records
- Supplier-order schedules
- Supplier confirmations
- Contracts and price schedules
- Goods-receipt records
- Inspection and rejection reports
- Supplier-return records
- Invoice and credit-note records
- Procurement cost reports
- Supplier scorecards
- Current improvement plans
Use information from the same supplier and reporting period.
2. Validate the procurement data
Before calculating performance:
- Confirm the reporting period.
- Check supplier, requisition and purchase-order references.
- Remove duplicate transactions.
- Confirm the required and actual dates.
- Verify ordered, delivered and accepted quantities.
- Separate supplier defects from internal or transport damage.
- Check approved price amendments.
- Reconcile goods receipts with invoices.
- Identify missing documentation.
- Record any data corrections.
3. Monitor practical procurement activities
Map and monitor the operational procurement workflow.
Requirement identified
↓
Purchase requisition approved
↓
Supplier selected
↓
Purchase order issued
↓
Supplier confirms the order
↓
Supplier delivers
↓
Goods are inspected and received
↓
Invoice is verified
↓
Payment is approved
Track whether each activity:
- Occurred on time
- Followed the approved procedure
- Used an authorised supplier
- Included the correct specification
- Received the required approval
- Produced complete documentation
- Was recorded in the relevant system
Procurement activity register
| Requisition | Supplier | Required action | Target date | Actual date | Status | Exception |
|---|---|---|---|---|---|---|
| REQ-101 | Supplier A | Issue purchase order | 3 July | 3 July | On time | None |
| REQ-102 | Supplier B | Issue purchase order | 4 July | 6 July | Late | Approval delay |
4. Measure supplier-order placement
Monitor the time from an approved requisition to the issue of the purchase order.
Use:
Purchase-order placement rate = Orders placed within target ÷ Total orders due × 100
Example:
- Orders due for placement: 100
- Orders placed within target: 88
Placement rate = 88 ÷ 100 × 100 = 88%
Measure purchase-order cycle time where required:
PO cycle time = Purchase-order issue date − Approved requisition date
Record delays caused by:
- Incomplete specifications
- Missing approval
- Budget queries
- Supplier selection
- Price confirmation
- System problems
- Procurement workload
5. Measure supplier on-time delivery
Define “on time” using the contractually confirmed delivery date and time.
Use:
Supplier on-time delivery = Deliveries received on time ÷ Total deliveries due × 100
Example:
- Deliveries due: 80
- Deliveries received on time: 72
On-time delivery = 72 ÷ 80 × 100 = 90%
Do not change the required date after delivery merely to improve reported performance. Record approved amendments separately.
6. Measure delivery in full
A delivery is in full when the supplier provides the complete ordered quantity.
Use:
Delivery-in-full rate = Deliveries received in full ÷ Total deliveries due × 100
Also calculate:
Unit fill rate = Units received ÷ Units ordered × 100
Example:
- Units ordered: 10,000
- Units received: 9,500
Unit fill rate = 9,500 ÷ 10,000 × 100 = 95%
7. Measure supplier OTIF
Supplier On-Time In-Full (OTIF) measures orders received both on time and in full.
Supplier OTIF = Deliveries received on time and in full ÷ Total deliveries due × 100
A complete but late delivery does not qualify. An on-time short delivery also does not qualify.
8. Monitor quality returns
Record materials or products returned to suppliers because of:
- Defects
- Incorrect specifications
- Damage attributable to the supplier
- Incorrect products
- Contamination
- Inadequate packaging
- Regulatory or quality failure
Use:
Quality return rate = Units returned for supplier-quality reasons ÷ Units received × 100
or:
Supplier acceptance rate = Units accepted ÷ Units inspected × 100
Quality-return register
| Supplier | PO | Material | Received | Returned | Reason | Corrective action |
|---|---|---|---|---|---|---|
| Supplier A | PO-501 | MAT-A | 1,000 | 50 | Defective material | Replacement required |
Track:
- Return authorisation
- Collection
- Replacement
- Credit note
- Root-cause response
- Corrective-action completion
9. Calculate procurement cost per unit
Include applicable operational procurement costs:
- Purchase price
- Freight
- Customs and duties
- Handling
- Inspection
- Order administration
- Expediting
- Returns
- Rework caused by supplier failure
Use:
Procurement cost per accepted unit = Total procurement cost ÷ Accepted units
Example:
- Total procurement cost: R550,000
- Accepted units: 10,000
Cost per accepted unit = R550,000 ÷ 10,000 = R55
Compare this with the approved budget or standard cost.
Cost variance
Cost variance per unit = Budgeted cost per unit − Actual cost per accepted unit
A negative result indicates that actual cost is above budget.
10. Prepare the procurement scorecard
| Performance measure | Target | Actual | Variance | Status |
|---|---|---|---|---|
| PO placement within target | 95% | 88% | −7% | Below target |
| Supplier on-time delivery | 95% | 90% | −5% | Below target |
| Delivery in full | 98% | 94% | −4% | Below target |
| Supplier OTIF | 94% | 86% | −8% | Below target |
| Quality return rate | ≤1% | 3% | 2% over | Below target |
| Cost per accepted unit | R50 | R55 | R5 over | Above budget |
Ensure that every result is supported by traceable source records.
11. Analyse performance by supplier
Do not rely only on the combined procurement result. Evaluate each supplier separately.
| Supplier | On-time | In full | OTIF | Quality returns | Cost per unit |
|---|---|---|---|---|---|
| Supplier A | 97% | 99% | 96% | 0.5% | R48 |
| Supplier B | 82% | 90% | 76% | 5% | R60 |
Supplier-level analysis identifies where corrective action is required.
12. Identify performance gaps
For every KPI:
- Confirm the target.
- Calculate actual performance.
- Determine the variance.
- Identify affected suppliers and orders.
- Determine the effect on operations.
- Rate the priority.
- Record the supporting evidence.
Performance-gap register
| Gap | Affected supplier | Operational effect | Priority | Required investigation |
|---|---|---|---|---|
| Low on-time delivery | Supplier B | Production delays | High | Capacity and dispatch process |
| High quality returns | Supplier B | Rework and stock shortage | High | Supplier quality controls |
| High unit cost | Multiple | Budget exceeded | Moderate | Expediting and return costs |
13. Determine operational effects
Procurement failures may affect:
- Production continuity
- Warehouse replenishment
- Customer orders
- Inventory levels
- Transport schedules
- Quality
- Working capital
- Cost
- Supplier relationships
- Contract compliance
Link each procurement gap to the affected downstream operation.
14. Identify root causes
Investigate the underlying cause.
| Performance problem | Possible root cause |
|---|---|
| Late order placement | Approval delay or incomplete specification |
| Late supplier delivery | Capacity shortage or poor supplier planning |
| Short delivery | Material shortage or allocation failure |
| Quality returns | Weak supplier quality assurance |
| High cost per unit | Poor consolidation, expediting or price variance |
| Low OTIF | Combined delivery and quantity failures |
| Missing information | Weak system or document controls |
Use evidence and an appropriate root-cause method such as the Five Whys.
15. Take immediate containment action
Possible containment measures include:
- Expedite a critical order.
- Arrange a partial delivery.
- Use an approved backup supplier.
- Transfer stock from another location.
- Isolate defective materials.
- Obtain a replacement or credit.
- Correct an inaccurate purchase order.
- Inform affected production and customer-service teams.
- Prioritise inspection and receiving.
Containment must address the immediate operational risk without bypassing procurement controls.
16. Develop the performance-improvement plan
| Performance gap | Root cause | Improvement action | Owner | Due date | Success measure |
|---|---|---|---|---|---|
| PO placement below target | Slow approval | Introduce automated approval alerts | Procurement manager | 20 August | Placement ≥95% |
| Late delivery | Supplier capacity constraint | Implement confirmed capacity plan | Supplier manager | 31 August | On-time ≥95% |
| High quality returns | Weak final inspection | Add supplier pre-dispatch checks | Quality manager | 25 August | Returns ≤1% |
Include:
- Immediate containment
- Permanent corrective action
- Responsible person
- Resources
- Due date
- Target
- Monitoring frequency
- Escalation point
17. Monitor improvement
Track:
- Purchase-order cycle time
- Supplier confirmations
- Delivery status
- On-time and in-full results
- Quality returns
- Credits and replacements
- Cost performance
- Corrective-action completion
Where performance remains below target, escalate it through the supplier and contract-management process.
18. Prepare the procurement-performance report
Include:
- Reporting period
- Data sources
- Operational activity results
- Supplier-order placement
- On-time and in-full performance
- Supplier OTIF
- Quality returns
- Cost per accepted unit
- Target variances
- Root causes
- Operational effects
- Improvement actions
- Remaining risks
- Recommendations
Practical task
You are provided with procurement-performance reports, supplier-order records and approved criteria.
Complete the following:
- Validate the procurement data.
- Measure operational procurement activities.
- Calculate purchase-order placement performance.
- Calculate supplier on-time delivery.
- Calculate delivery in full and supplier OTIF.
- Calculate quality-return performance.
- Calculate procurement cost per accepted unit.
- Prepare an overall and supplier-level scorecard.
- Identify performance gaps and downstream effects.
- Conduct root-cause analysis.
- Develop a performance-improvement plan.
- Prepare a procurement-performance report.
Required evidence
Include the following in your Portfolio of Evidence:
- Source operational plan and targets
- Data-validation record
- Procurement activity register
- Purchase-order placement calculations
- Supplier on-time and in-full calculations
- Supplier OTIF calculation
- Quality-return register and calculation
- Cost-per-unit calculation
- Overall procurement scorecard
- Supplier-level scorecards
- Performance-gap register
- Root-cause analysis
- Containment actions
- Performance-improvement plan
- Monitoring records
- Procurement-performance report
- Evidence of review or approval
- Completed observation checklist
- Learner declaration of authenticity
Competence checklist
| Assessment criterion | Competent | Not yet competent | Comments |
|---|---|---|---|
| Validate procurement-performance information | |||
| Monitor operational procurement activities | |||
| Measure supplier-order placement | |||
| Measure supplier on-time delivery | |||
| Measure supplier delivery in full | |||
| Calculate supplier OTIF | |||
| Measure supplier-quality returns | |||
| Calculate procurement cost per accepted unit | |||
| Compare actual performance with targets | |||
| Analyse performance by supplier | |||
| Identify downstream operational effects | |||
| Determine root causes of non-performance | |||
| Develop an appropriate improvement plan | |||
| Monitor improvement actions | |||
| Prepare a comprehensive procurement report | |||
| Submit complete supporting evidence |
Lesson Summary
To monitor procurement and supply activities, validate procurement records and measure purchase-order placement, supplier on-time delivery, delivery in full, OTIF, quality returns and cost per accepted unit. Compare actual performance with approved targets, analyse individual suppliers and determine the downstream effect of procurement failures. Identify root causes, apply appropriate containment and develop a measurable improvement plan. Monitor corrective actions until supplier and procurement performance meet operational requirements.